Construction Schedule
Construction Schedule Important Contacts Sponsorship Opportunities Sponsors
The following schedule is tentative. It will be adjusted as needed.
7/27- 8/4 - East Ayer - Front Street to Brainard
8/5 - 8/17 - East Ayer - Brainard to Sumner
8/18 - 8/31 - East Ayer - Sumner to 5-Corners
9/1 - 9/14 - West Ayer - Front Street to Brainard
9/15 - 9/28 - West Ayer - Brainard to Sumner
9/29 - 10/13 - West Ayer - Sumner to 5-Corners
10/14 - 10/31 - Finals Surfacing
The following schedule is tentative. It will be adjusted as needed.
7/27- 8/4 - East Ayer - Front Street to Brainard
8/5 - 8/17 - East Ayer - Brainard to Sumner
8/18 - 8/31 - East Ayer - Sumner to 5-Corners
9/1 - 9/14 - West Ayer - Front Street to Brainard
9/15 - 9/28 - West Ayer - Brainard to Sumner
9/29 - 10/13 - West Ayer - Sumner to 5-Corners
10/14 - 10/31 - Finals Surfacing
Latest page update: made by HarvardMainStreet
, Jul 23 2008, 10:01 AM EDT
(about this update
About This Update
Edited by HarvardMainStreet
49 words added
50 words deleted
view changes
- complete history)
Edited by HarvardMainStreet
49 words added
50 words deleted
view changes
- complete history)
Keyword tags:
construction schedule
downtown
Harvard
More Info: links to this page