The following schedule is tentative. It will be adjusted as needed.

7/27- 8/4 - East Ayer - Front Street to Brainard

8/5 - 8/17 - East Ayer - Brainard to Sumner

8/18 - 8/31 - East Ayer - Sumner to 5-Corners

9/1 - 9/14 - West Ayer - Front Street to Brainard

9/15 - 9/28 - West Ayer - Brainard to Sumner

9/29 - 10/13 - West Ayer - Sumner to 5-Corners

10/14 - 10/31 - Finals Surfacing


No user avatar
HarvardMainStreet
Latest page update: made by HarvardMainStreet , Jul 23 2008, 10:01 AM EDT (about this update About This Update HarvardMainStreet Edited by HarvardMainStreet

49 words added
50 words deleted

view changes

- complete history)
More Info: links to this page
There are no threads for this page.  Be the first to start a new thread.

Related Content

  (what's this?Related ContentThanks to keyword tags, links to related pages and threads are added to the bottom of your pages. Up to 15 links are shown, determined by matching tags and by how recently the content was updated; keeping the most current at the top. Share your feedback on Wetpaint Central.)